Expo 2027 Belgrade: Government Report Puts the Expo’s Future in Parliament’s Hands

The caretaker government is preparing a full report on Expo 2027 for the new majority, which the Ministry of Finance expects to decide whether the project continues.
Expo 2027 Belgrade: Government Report Puts the Expo's Future in Parliament's Hands

Serbia's caretaker government is preparing a comprehensive report on Expo 2027 Belgrade that will be sent to the new parliamentary majority, and the Ministry of Finance says it expects that majority to state its position on the future of the project. This makes parliament, where the Student List won a majority in the 25 October elections, the place where the question of continuing the exhibition is now expected to be answered. For contractors, exhibitors and suppliers, it means the decisive signal on Expo 2027 is likely to come from the new majority, not from the outgoing government.

The report was first described by the news site Radar on 26 November and confirmed by the Ministry of Finance to the Tanjug agency on 27 November. In the same week, the Bureau International des Expositions (BIE) explained what cancellation would mean in practice, and a lawyer published a draft government decision on €11 million for guarantees linked to Expo contracts.

What did the government announce?

According to the Ministry of Finance, the report will give an overview of the current state of construction and of the activities undertaken to prepare the exhibition. After it is considered and adopted at a session of the caretaker government, it will be forwarded to the parliamentary majority. The ministry said it expects the majority, on the basis of this overview, to state its position on the further fate of the project and on continuing the activities needed to hold the Expo.

Radar, citing sources close to the office of outgoing Prime Minister Đuro Macut, reported that the government plans to adopt the report at a session next week. According to Radar, the Student List holds a majority of 140 MPs in the new National Assembly. No date for the session or for a parliamentary debate had been announced in the sources reviewed for this article.

What will the report cover, and how much has been spent?

According to Radar's source, the report will cover two areas:

  • Construction of the facilities in the Expo complex in Surčin, which is the responsibility of the Construction Directorate of Serbia;
  • Organisation of the exhibition, which is the responsibility of the state-owned company EXPO 2027 d.o.o.

Radar reported that EXPO 2027 d.o.o. was founded on 18 December 2023 with initial capital of one million dinars, and that its capital was increased by 8.6 billion dinars by 18 June 2026.

On costs, Radar recalled that the Ministry of Finance's Fiscal Strategy put the Expo at about €1.22 billion, plus €75 million for equipment, hangars and related facilities and €509 million for line infrastructure and a heat source, or just over €1.7 billion in total. By Radar's own calculation, about 163.8 billion dinars (around €1.4 billion) has been spent from the budget so far, not counting the National Stadium and the railway to it. Radar reported that around €71.3 million was paid in October alone. These are the outlet's figures; the official report has not been published.

What does the BIE say about cancellation?

Answering questions from Biznis.rs, as reported by B92 on 25 November, the BIE said its rules provide for compensation, not penalty fees. According to the BIE:

  • only the host country can decide to withdraw from organising an Expo, and Serbia has taken no such decision;
  • if it did, the organiser would have to reimburse participating countries for justified costs arising directly from their participation, with the state as guarantor;
  • the amounts would be set by the BIE General Assembly, so they cannot be estimated in advance;
  • changing the dates would need a two-thirds majority of the General Assembly, which the BIE says is practically no longer possible with less than six months to go.

The BIE added that changes of government before or even during an Expo are normal, and that it will work with everyone involved so the exhibition opens on 15 May 2027. Pavilion handovers are scheduled to start, gradually, on 1 December.

What is the dispute over the €11 million?

On 21 November, lawyer Ivan Ninić published on X what he presented as documentation of a planned caretaker government decision to recapitalise the state export credit agency AOFI by €11 million, so that it could provide bank guarantees for companies working on Expo 2027, the weekly Vreme reported. Ninić, a critic of the outgoing government, said guarantees for domestic construction are not AOFI's primary activity under its founding law and that this role was added by special government acts. He described the plan as a misuse of public money.

The government has not publicly commented on these claims in the sources reviewed, and exponews.rs could not confirm whether the decision was adopted.

What do the outgoing government and the new majority say?

Outgoing Finance Minister Siniša Mali told N1 on 19 November that preparations had slowed because people responsible were afraid to sign decisions, and warned that without continued preparations there would be no Expo, with possible damage to Serbia's reputation and possible lawsuits.

Student List MP Sanja Fric told N1 that the new majority is aware of Serbia's international obligations, but that responsibility for delays lies with the caretaker government, which still manages the project through the Ministry of Finance. According to N1, the Student List's priorities are a safety assessment of what has been built and a review of projects linked to the Expo.

What it means for exhibitors, contractors and suppliers

  • Expect a decision point in parliament. Once the report is adopted and sent, the new majority's position will be the key signal for contracts and schedules.
  • No cancellation has been decided. The BIE says Serbia has not withdrawn, and the handover programme starts on 1 December.
  • Document everything. The report and planned reviews will look at contracts and spending. Keep tenders, change orders, deliveries, guarantees and payments fully documented.
  • Check your guarantees. If your contract depends on bank or state-agency guarantees, confirm with your bank and client which instrument applies and whether it is in force.
  • Plan for both scenarios. Foreign participants' fit-out work continues on their own timetables; domestic suppliers should keep cash flow buffers until the political picture is clear.

Key facts

  • Expo 2027 Belgrade is scheduled for 15 May – 15 August 2027 in Surčin.
  • The caretaker government will adopt a report on Expo 2027 and send it to the parliamentary majority, according to the Ministry of Finance (27 November).
  • The Student List holds 140 seats in the new Assembly, according to Radar.
  • About €1.4 billion spent so far, according to Radar's calculation; the Fiscal Strategy total was just over €1.7 billion.
  • BIE rules provide for compensation of participants' justified costs, not penalties.
  • A draft decision on €11 million for AOFI guarantees was published by lawyer Ivan Ninić; adoption is unconfirmed.