Preparations for Expo 2027 Belgrade have slowed, an adviser to the director of EXPO 2027 d.o.o. said on 20 November, and the state company is asking the Student List, which won the 25 October elections but has not yet formed a government, for a clear decision on the project. The open question of who decides – the caretaker cabinet or the incoming majority – now hangs over the 1 December start of pavilion handovers and the winter fit-out season that contractors are planning around. This week the organiser, the caretaker finance minister and the Student List all set out their positions in public; none has announced a formal decision.
What did the organiser say this week?
Dušan Borovčanin, adviser to the director of EXPO 2027, said on Radio Beograd, as reported by Tanjug and carried by Objektiv, that there had been some slowing of works and that people on the project are working in uncertainty. He asked for a clear signal at the strategic level – whether the project continues in full, continues at all, or the company is wound up – so that teams have instructions. According to his statements:
- the next two months are critical, with concrete answers needed above all from the new government;
- there have been no official meetings between EXPO 2027 and the Student List, but the company is open to talks;
- adoption of the budget for 2027 is particularly important for the company;
- 111 participation contracts have been signed out of 145 confirmed participants;
- possibly fewer than 10% of participants have applied for temporary building permits so far, with more applications expected within days;
- a large number of participants will not be ready to take over their spaces on 1 December, which he said was never meant as the completion date for the whole complex, only for the international participants' zone.
Borovčanin said Serbia could still cancel the Expo unilaterally, but would then bear full responsibility towards participants and the Bureau International des Expositions (BIE). Some countries spend from several million to more than €20 million on taking part, he said, and in his view the total owed to participants would exceed several hundred million euros. He added that he nevertheless expects the Expo to take place in its planned scope, and that no participant he spoke to at the BIE General Assembly in Paris raised withdrawal or postponement.
What does the caretaker government say?
Caretaker Finance Minister Siniša Mali said on TV Tanjug on 18 November that work is continuing, but slowly, and that if documents are not signed and the process does not continue, there will be no Expo, Vreme reported. On 20 November, speaking on Pink TV, he again appealed to the Student List to decide what it will do with the project, according to Tanjug. He said people had stopped working because of what he described as an atmosphere of fear, and that the list had made contradictory statements on whether the Expo would be held. He also said that, as far as he knew, the deadline for forming a new government falls around mid-February.
Mali is an official of the Serbian Progressive Party, which lost the elections. Vreme noted that his assessments represent the view of one side.
What does the Student List say?
Student List MP Sanja Fric told Nova.rs on 19 November that the list has not yet taken over the levers of power and has no formal authority over the project. In her view, responsibility for its pace, delays, potentially corrupt contracts and breaches of procedure lies solely with the caretaker government. She said obligations already taken on must be respected, but that the safety of participants and future users of the buildings must come first, and that the 1 December handover is a question for the outgoing government. Once a government is formed, she said, an expert team will review the project and present a strategy to the public and the international community.
The list's economy and finance programme, published on 14 November and summarised by N1 and Moj Novi Sad, sets out its approach:
- the special laws for Belgrade Waterfront, Expo 2027 and line infrastructure will be reviewed, with proposals to repeal them, amend them or align them with general rules, each with an assessment of arbitration risk;
- for projects already under way, the State Audit Institution and an independent technical auditor would publish the real cost and outstanding obligations, and an independent commission's report would guide whether a project continues, changes or is suspended;
- Serbia would not act unilaterally where ratified international agreements apply;
- the public procurement portal would publish the full text of every contract, with prices and bid scoring; single-bid procedures and large annexes would be flagged and referred to the Budget Inspection, and a three-year blacklist would apply to anyone who breaches a contract.
Earlier, on 5 November, Student List candidate Danijela Milovanović Rodić told Vreme that cancelling the Expo would be neither responsible nor serious, but that it would not be held at any cost before the real state of the works is known. Borovčanin said this week that all contracts and procurement calls of EXPO 2027 had been public and transparent.
Who is responsible for what?
As Borovčanin described the structure, the Government of Serbia holds the obligation towards the BIE. The Ministry of Finance is the investor; it entrusted management of construction to the Construction Directorate of Serbia (Građevinska direkcija Srbije), which works with the general contractor Power China. EXPO 2027 d.o.o. coordinates the exhibition and relations with the BIE. He said the company has not yet taken over management of the whole site and hopes to do so in the coming days. BIE Secretary General Dimitri Kerkentzes has told Vreme that the BIE has no role in awarding, managing or auditing public contracts, which fall under Serbian law.
In a separate development, N1 reported on 20 November that EXPO 2027 had withdrawn from negotiations to act as general sponsor of a Belgrade Philharmonic concert with pianist Lang Lang, planned for 13 December at Sava Centar. The orchestra said the concert has been postponed.
What it means for exhibitors, contractors and suppliers
- 1 December is a rolling start, not a single date. According to the organiser, each country can take over only after its temporary building permit is approved and it has a local legal entity and designers in place. Confirm your client's permit status before mobilising crews.
- Watch two milestones: the formation of a new government and the adoption of the 2027 budget. Both affect decisions at EXPO 2027 d.o.o., according to Borovčanin and Mali.
- Prepare for more transparency. If the Student List programme is implemented, full contract texts, prices and annexes would become public. Keep pricing and change orders well documented.
- Unsigned deals are not commitments. The withdrawal from the Philharmonic sponsorship talks shows that negotiations can end before a contract is signed.
- Pavilion work continues on the participants' side. More than 70 participants receive support from Serbia for their pavilions, Borovčanin said, while the most developed countries finance their own and are largely ready.
Key facts
- Expo 2027 Belgrade runs from 15 May to 15 August 2027.
- Pavilion handovers are due to start on 1 December 2026; the organiser expects many participants to take over later.
- 111 participation contracts signed, 145 participants confirmed (EXPO 2027, 20 November).
- Fewer than 10% of participants had applied for temporary building permits, according to Borovčanin.
- More than 21,000 volunteers registered against a plan of 20,000.
- The Student List plans to review the Expo 2027 special law and publish all state contracts in full.