Expo 2027: BIE Says Postponement Is No Longer Possible, Handover 1 December

BIE Secretary General Dimitri Kerkentzes says moving Expo 2027 dates would need a two-thirds vote and BIE deadlines no longer allow it. Participants move in on 1 December.
Expo 2027: BIE Says Postponement Is No Longer Possible, Handover 1 December

The dates of Expo 2027 Belgrade are effectively locked. In an interview with the weekly Vreme published on 11 November, Dimitri Kerkentzes, Secretary General of the Bureau International des Expositions (BIE), said a postponement is "practically no longer possible". Participating countries will start taking over their exhibition spaces on 1 December, as planned. For pavilion builders, fit-out crews and suppliers, the message is that the schedule to the 15 May 2027 opening stands, whatever happens in Serbian politics.

exponews.rs reported the BIE's earlier comments on 6 and 11 November. What is new is the BIE's explanation of why the dates cannot move, and a clear statement of what the BIE does and does not control on procurement and building safety.

Why the dates cannot change

According to Kerkentzes, the dates of 15 May to 15 August 2027 were fixed by BIE member states when the Expo was officially recognised on 26 November 2024. Any change would need:

  • approval by the BIE General Assembly
  • a two-thirds majority of member states

With just over six months to go, he said, BIE regulatory deadlines practically rule out such a change. More than 140 participants have planned around the fixed dates, and all efforts are aimed at opening on 15 May.

The question was asked because Serbia has not yet formed a new government after the 25 October election. Kerkentzes said elections are a normal part of democratic life and that changes of government often happen before or even during an Expo. He said the BIE will contact the new government as soon as it is formed.

Handover on 1 December

Kerkentzes said preparations are on schedule and participants are well advanced. They will begin taking over their spaces from 1 December, and he described the coming weeks as crucial, with keeping up the current pace a shared responsibility.

He also listed who has a role in getting pavilions ready on time: the organiser, participating countries bringing their exhibits and teams, and Serbian institutions from the Customs Administration to the National Bank of Serbia, as well as companies working on the site.

What the BIE does not do

On procurement and special laws, Kerkentzes drew clear lines:

  • Procurement and public money are the host country's responsibility under Serbian law. The BIE has no role in awarding, managing or auditing public contracts.
  • The choice of domestic legal instruments, including the special law for Expo, is a matter for Serbian institutions. The project must still comply with the 1928 Paris Convention, BIE rules and obligations to participants.
  • The BIE oversees the exhibition and its site, but not other public or private projects linked to it.
  • Buildings must meet Serbian construction and fire safety rules. The Expo's special regulations set out how these apply to the site, taking into account that many structures are temporary. Pre-opening inspections are carried out by Serbian authorities.

Volunteers pass 20,000

Separately, Expo 2027 d.o.o. said on 11 November that more than 20,000 people from over 145 countries have applied to volunteer, up from the 18,000 reported at the end of October. According to Tanjug, 37.3% of applications come from abroad.

What it means for contractors and exhibitors

  • Plan to the fixed calendar. With a postponement ruled out by the BIE, crews and material deliveries for national pavilions should be booked for December–April without waiting for political decisions.
  • Expect the inspection to be Serbian. Fire and construction compliance will be checked by Serbian authorities before opening. Keep fire certificates for materials, structural calculations and as-built documentation ready.
  • Customs is on the critical path. Kerkentzes named the Customs Administration among the institutions that must deliver. Exhibitors importing exhibits and stand materials should confirm temporary-import procedures early.
  • Procurement questions stay domestic. Any review of Expo contracts by the new government is a Serbian matter, not a BIE one. Suppliers on state contracts should keep documentation complete.