Expo 2027 Tells BIE Assembly Site Is 85% Built, With 144 Participants

At the BIE General Assembly in Paris, the Expo 2027 organiser reported 85% of construction done, 144 confirmed participants and a March 2027 meeting on site.
Expo 2027 Tells BIE Assembly Site Is 85% Built, With 144 Participants

The organiser of Expo 2027 Belgrade told member states of the Bureau International des Expositions (BIE) on 17 November 2026 that overall construction on the Expo site in Surčin is 85% complete. Addressing the 179th BIE General Assembly in Paris, the chief executive of EXPO 2027 d.o.o. Beograd, Danilo Jerinić, said the exhibition remains a firm national commitment and an international responsibility for Serbia. The report had been awaited: in the days before the meeting, the BIE asked Serbian authorities to confirm that works were on schedule and that participants could start taking over their pavilions from 1 December. With the opening set for 15 May 2027, the figures matter directly to the contractors who will fit out more than a hundred national pavilions over the winter.

What the organiser reported

Jerinić acknowledged the current political and social situation in Serbia and the attention it draws from international partners, and said all relevant institutions were working to ensure continuity of preparations, according to Biznis.rs. The progress report itself was presented by Dušan Borovčanin, adviser to the director. He said:

  • structural works are being completed and buildings closed across the site, so that teams can start installing building systems and interior finishes, while construction continues elsewhere
  • in the zone for best practices and corporate content, work is under way on facades and weather protection, and buildings that are ready are getting installations and interior finishing
  • in the thematic zone, structural works are nearing completion, and installation of exhibition content is being coordinated with the remaining building works
  • asphalting of roads is finished; footpaths, green areas and other public spaces are still being landscaped
  • construction of the Expo Village is complete, and furnishing, equipment installation and preparation for operation are under way

Borovčanin described the next major stage as the gradual handover of pavilions to official participants. The published accounts of his speech do not give a date for the first handovers or say whether all spaces will be ready on 1 December.

Participants, designers and a March meeting

According to the organiser, the Expo now has 144 confirmed official participants, and 111 participation contracts have been signed. Borovčanin urged countries building their own pavilions to appoint lead designers without delay if they have not already done so, and to speed up the submission of concept and preliminary designs. He said these are not formalities but preconditions for moving to the permit and construction phases.

He also announced that the third International Participants Meeting (IPM 3) is planned for 2–4 March 2027 on the Expo site in Belgrade. More than 20,000 volunteers have registered, and applications remain open.

Pressure from Paris and a new government

The BIE had told Tanjug, as reported by UNA on 14 November, that more than 140 participants had planned their work around the 1 December date and that the coming weeks were critical. It stressed that works must continue at full intensity while responsibilities are handed over smoothly to Serbia's new government. The BIE secretary general has said a change of dates would require a two-thirds majority of member states.

Biznis.rs reports that the Student List, which won last month's parliamentary elections, plans to review special laws and contracts for Expo 2027 and other infrastructure projects while respecting international obligations. Its leader, Ilija Srdanović, has said Serbia must honour its Expo commitments, with priority on institutions that can transparently control public spending.

What it means for contractors and suppliers

  • Fit-out is the next bottleneck. With structures closing, the organiser's stated priorities are technical checks and safe access for contractors working on pavilion interiors. Expect site access rules, accreditation and delivery slots to tighten.
  • Self-build pavilions are behind the curve. The public appeal to appoint lead designers suggests some participants have not yet fixed design teams. Architects, engineers and permit specialists may still find work there, but timelines will be compressed.
  • Mark 2–4 March 2027. IPM 3 will bring commissioners and pavilion teams to Belgrade, a key moment for suppliers seeking meetings.
  • Watch the handover dates. Until participants confirm keys in hand, build schedules that start on 1 December should carry a buffer.

Expo 2027 Belgrade runs from 15 May to 15 August 2027.